ITAC Assessment: OR0823
ITAC logo
ITAC Assessment: OR0823
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Molded pulp fiber
NAICS 322299: All Other Converted Paper Product Manufacturing
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $500
k
to 1
M
# of Employees 55
Plant Area 116,000
ft2
Annual Production 7,100,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $131,261 3,325,800
kWh
Electricity Demand $89,633 6,366
kW-mo/yr
Electricity Fees $11,889 -
Natural Gas $247,792 49,340
MMBtu
TOTAL YEARLY COSTS $480,575
RECOMMENDED SAVINGS* $18,960 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,477 - $3,267
42,900
kWh
$1,210
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,084 $7,862 $1,662
21,825
kWh
$422
-
kW-mo/yr
-
03 2.2314: Replace heat treating oven with more efficient unit $12,399 $275,013 - - $12,399
-
MMBtu
TOTAL RECOMMENDED $18,960 $282,875 $4,929
64,725
kWh
$1,632
-
kW-mo/yr
$12,399
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs