ITAC Assessment: OR0814
ITAC logo
ITAC Assessment: OR0814
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Modular Buildings
NAICS 236220: Commercial and Institutional Building Construction
SIC 1542: General Contractors-Nonresidential Buildings, Other than Industrial Buildings and Warehouses
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 150,000
ft2
Annual Production 300
units
Production Hrs. Annual 3,510
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $40,449 696,440
kWh
Electricity Demand $20,371 2,983
kW-mo/yr
Electricity Fees $3,138 -
Natural Gas $60,445 4,805
MMBtu
TOTAL YEARLY COSTS $124,403
RECOMMENDED SAVINGS* $30,520 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.7221: Lower temperature during the winter season and vice-versa $13,621 - - - $13,621
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,149 $27,485 $9,542
96,149
kWh
$2,551
-
kW-mo/yr
- $2,056
03 2.7491: Insulate glazing, walls, ceilings, and roofs $2,750 $19,901 - - $2,750
-
MMBtu
-
TOTAL RECOMMENDED $30,520 $47,386 $9,542
96,149
kWh
$2,551
-
kW-mo/yr
$16,371
-
MMBtu
$2,056
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs