Assessment Year | 2025 |
---|---|
Principal Product | SDD powder |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
50,000
ft2
|
Annual Production | 580
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $371,220 | 4,900,200 |
kWh
|
$0.076 | |
Electricity Demand | $129,913 | 9,624 |
kW-mo/yr
|
$13.50 | |
Electricity Fees | $642 | - |
|
- | |
Natural Gas | $121,113 | 13,681 |
MMBtu
|
$8.85 | |
Waste Disposal Costs | |||||
Water Usage | $29,234 | 9,750 |
Tgal
|
$3.00 | |
Water Disposal | $61,274 | 10,627 |
Tgal
|
$5.77 | |
TOTAL YEARLY COSTS | $713,396 | ||||
RECOMMENDED SAVINGS* | $212,078 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 4.212: Adopt in-house material generation | $165,269 | $363,639 |
$(-12,530.0)
(-165,384)
kWh
|
$(-3,058.0)
-
kW-mo/yr
|
$180,857 | |
02 | 2.4322: Use or replace with energy efficient substitutes | $4,192 | - |
$3,369
44,466
kWh
|
$823
-
kW-mo/yr
|
- | |
03 | 2.9114: Use solar heat to make electricty | $42,617 | $404,426 |
$28,188
372,328
kWh
|
$14,429
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $212,078 | $768,065 |
$19,027
251,410
kWh
|
$12,194
-
kW-mo/yr
|
$180,857 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs