| Assessment Year | 2025 |
|---|---|
| Principal Product | Treated wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 4 |
| Plant Area |
1,325,904
ft2
|
| Annual Production | 1,170,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $85,507 | 1,184,640 |
kWh
|
$0.072 | |
| Electricity Demand | $36,050 | 2,477 |
kW-mo/yr
|
$14.55 | |
| Electricity Fees | $9,690 | - |
|
- | |
| Natural Gas | $6,203 | 527 |
MMBtu
|
$11.77 | |
| Waste Disposal Costs | |||||
| Water Usage | $1 | 1,170,000 |
Tgal
|
$0.000 | |
| TOTAL YEARLY COSTS | $137,451 | ||||
| RECOMMENDED SAVINGS* | $37,252 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $2,572 | - | - | - |
$2,572
-
MMBtu
|
|
| 02 | 2.6127: Maintain air filters by cleaning or replacement | $1,470 | - |
$1,470
20,367
kWh
|
- | - | |
| 03 | 2.4322: Use or replace with energy efficient substitutes | $7,728 | - |
$7,728
107,064
kWh
|
- | - | |
| 04 | 2.9114: Use solar heat to make electricty | $25,482 | $102,430 |
$16,240
224,937
kWh
|
$9,242
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $37,252 | $102,430 |
$25,438
352,368
kWh
|
$9,242
-
kW-mo/yr
|
$2,572
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs