ITAC Assessment: OR0794
ITAC logo
ITAC Assessment: OR0794
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Manufactured homes
NAICS 321991: Manufactured Home (Mobile Home) Manufacturing
SIC 2451: Mobile Homes
Sales Range $50
M
to 100
M
# of Employees 212
Plant Area 168,000
ft2
Annual Production 880
units
Production Hrs. Annual 6,120
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,391 720,914
kWh
Electricity Demand $40,784 2,992
kW-mo/yr
Electricity Fees $5,097 -
Natural Gas $19,906 1,856
MMBtu
LPG $14,463 621
MMBtu
TOTAL YEARLY COSTS $128,641
RECOMMENDED SAVINGS* $51,372 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Administrative Changes Savings
01 2.6231: Utilize controls to operate equipment only when needed $1,236 $1,629 - - $1,236
-
MMBtu
- - -
02 2.4239: Eliminate or reduce compressed air usage $2,287 $5,523 $2,287
34,077
kWh
- - - - -
03 2.1321: Replace fossil fuel equipment with electrical equipment $20,545 $92,473 $(-9,181.0)
(-136,782)
kWh
- - $14,463
-
MMBtu
$12,590 $2,673
04 2.9114: Use solar heat to make electricty $12,662 $67,250 $8,246
122,809
kWh
$4,416
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,153 $7,546 $1,153
17,180
kWh
- - - - -
06 2.4322: Use or replace with energy efficient substitutes $13,489 $12,623 $6,898
102,765
kWh
$6,591
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $51,372 $187,044 $9,403
140,049
kWh
$11,007
-
kW-mo/yr
$1,236
-
MMBtu
$14,463
-
MMBtu
$12,590 $2,673
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs