ITAC Assessment: OR0791
ITAC logo
ITAC Assessment: OR0791
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Formaldehyde & Urea-formaldehyde
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 100,000
ft2
Annual Production 180,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $584,865 9,925,000
kWh
Electricity Demand $148,734 16,275
kW-mo/yr
Electricity Fees $33,851 -
Natural Gas $178,020 64,217
MMBtu
Other Gas $22,883 1
MMBtu
Waste Disposal Costs
Water Usage $48,228 15,359
Tgal
TOTAL YEARLY COSTS $1,016,581
RECOMMENDED SAVINGS* $34,770 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings
01 4.463: Modify facility to avoid excess maintenance costs $29,053 $352,000 $553
9,463
kWh
- - $28,500
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,032 - $736
12,588
kWh
$296
-
kW-mo/yr
- -
03 2.3212: Optimize plant power factor $2,606 $17,324 - - $2,606 -
04 2.2136: Install / repair insulation on steam lines $2,079 $5,750 $2,079
35,547
kWh
- - -
TOTAL RECOMMENDED $34,770 $375,074 $3,368
57,598
kWh
$296
-
kW-mo/yr
$2,606 $28,500
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs