| Assessment Year | 2024 |
|---|---|
| Principal Product | Formaldehyde & Urea-formaldehyde |
| NAICS | 325211: Plastics Material and Resin Manufacturing |
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $10 M to 50M |
| # of Employees | 30 |
| Plant Area |
100,000
ft2
|
| Annual Production | 180,000,000
lb
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $584,865 | 9,925,000 |
kWh
|
$0.059 | |
| Electricity Demand | $148,734 | 16,275 |
kW-mo/yr
|
$9.14 | |
| Electricity Fees | $33,851 | - |
|
- | |
| Natural Gas | $178,020 | 64,217 |
MMBtu
|
$2.77 | |
| Other Gas | $22,883 | 1 |
MMBtu
|
$22,883.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $48,228 | 15,359 |
Tgal
|
$3.14 | |
| TOTAL YEARLY COSTS | $1,016,581 | ||||
| RECOMMENDED SAVINGS* | $34,770 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $31,132 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.463: Modify facility to avoid excess maintenance costs | $29,053 | $352,000 |
$553
9,463
kWh
|
- | - | $28,500 | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,032 | - |
$736
12,588
kWh
|
$296
-
kW-mo/yr
|
- | - | |
| 03 | 2.3212: Optimize plant power factor | $2,606 | $17,324 | - | - | $2,606 | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $2,079 | $5,750 |
$2,079
35,547
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $34,770 | $375,074 |
$3,368
57,598
kWh
|
$296
-
kW-mo/yr
|
$2,606 | $28,500 | ||
| TOTAL IMPLEMENTED | $31,132 | $357,750 |
$2,632
45,010
kWh
|
- | - | $28,500 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs