ITAC Assessment: OR0779
ITAC logo
ITAC Assessment: OR0779
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Phase I/II clinical trial materials, Spray-dried drugs, Tablets/capsules
NAICS 325412: Pharmaceutical Preparation Manufacturing
SIC 2834: Pharmaceutical Preparations
Sales Range $100
M
to 500
M
# of Employees 125
Plant Area 33,750
ft2
Annual Production 10,000
units
Production Hrs. Annual 4,680
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,127 1,120,103
kWh
Electricity Demand $12,312 2,595
kW-mo/yr
Electricity Fees $10,033 -
Waste Disposal Costs
Water Usage $1,067 385
Tgal
TOTAL YEARLY COSTS $108,539
RECOMMENDED SAVINGS* $54,364 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 3.1161: Eliminate/reduce an operation $3,315 - $1,964
28,674
kWh
- $1,351
-
MMBtu
-
02 2.7124: Make a practice of turning off lights when not needed $2,749 - $2,749
40,174
kWh
- - -
03 4.212: Adopt in-house material generation $43,575 $54,837 $(-2,439.0)
(-35,609)
kWh
- - $46,014
04 2.9114: Use solar heat to make electricty $4,725 $57,101 $3,890
56,818
kWh
$835
-
kW-mo/yr
- -
TOTAL RECOMMENDED $54,364 $111,938 $6,164
90,057
kWh
$835
-
kW-mo/yr
$1,351
-
MMBtu
$46,014
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs