| Assessment Year | 2023 |
|---|---|
| Principal Product | Phase I/II clinical trial materials, Spray-dried drugs, Tablets/capsules |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $100 M to 500M |
| # of Employees | 125 |
| Plant Area |
33,750
ft2
|
| Annual Production | 10,000
units
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $85,127 | 1,120,103 |
kWh
|
$0.076 | |
| Electricity Demand | $12,312 | 2,595 |
kW-mo/yr
|
$4.74 | |
| Electricity Fees | $10,033 | - |
|
- | |
| Waste Disposal Costs | |||||
| Water Usage | $1,067 | 385 |
Tgal
|
$2.77 | |
| TOTAL YEARLY COSTS | $108,539 | ||||
| RECOMMENDED SAVINGS* | $54,364 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.1161: Eliminate/reduce an operation | $3,315 | - |
$1,964
28,674
kWh
|
- |
$1,351
-
MMBtu
|
- | |
| 02 | 2.7124: Make a practice of turning off lights when not needed | $2,749 | - |
$2,749
40,174
kWh
|
- | - | - | |
| 03 | 4.212: Adopt in-house material generation | $43,575 | $54,837 |
$(-2,439.0)
(-35,609)
kWh
|
- | - | $46,014 | |
| 04 | 2.9114: Use solar heat to make electricty | $4,725 | $57,101 |
$3,890
56,818
kWh
|
$835
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $54,364 | $111,938 |
$6,164
90,057
kWh
|
$835
-
kW-mo/yr
|
$1,351
-
MMBtu
|
$46,014 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs