Assessment Year | 2023 |
---|---|
Principal Product | Phase I/II clinical trial materials, Spray-dried drugs, Tablets/capsules |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 125 |
Plant Area |
33,750
ft2
|
Annual Production | 10,000
units
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $85,127 | 1,120,103 |
kWh
|
$0.076 | |
Electricity Demand | $12,312 | 2,595 |
kW-mo/yr
|
$4.74 | |
Electricity Fees | $10,033 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $1,067 | 385 |
Tgal
|
$2.77 | |
TOTAL YEARLY COSTS | $108,539 | ||||
RECOMMENDED SAVINGS* | $54,364 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.1161: Eliminate/reduce an operation | $3,315 | - |
$1,964
28,674
kWh
|
- |
$1,351
-
MMBtu
|
- | |
02 | 2.7124: Make a practice of turning off lights when not needed | $2,749 | - |
$2,749
40,174
kWh
|
- | - | - | |
03 | 4.212: Adopt in-house material generation | $43,575 | $54,837 |
$(-2,439.0)
(-35,609)
kWh
|
- | - | $46,014 | |
04 | 2.9114: Use solar heat to make electricty | $4,725 | $57,101 |
$3,890
56,818
kWh
|
$835
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $54,364 | $111,938 |
$6,164
90,057
kWh
|
$835
-
kW-mo/yr
|
$1,351
-
MMBtu
|
$46,014 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs