ITAC Assessment: OR0771
ITAC logo
ITAC Assessment: OR0771
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Plastic sheet/roll stock
NAICS 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $10
M
to 50
M
# of Employees 33
Plant Area 43,000
ft2
Annual Production 7,000,000
lb
Production Hrs. Annual 6,120
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $165,886 3,233,700
kWh
Electricity Demand $50,576 8,809
kW-mo/yr
Electricity Fees $7,827 -
Waste Disposal Costs
Water Usage $8,133 560
Tgal
TOTAL YEARLY COSTS $232,422
RECOMMENDED SAVINGS* $127,012 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Increase in Production Savings
01 2.4312: Improve lubrication practices $13,223 - $2,565
49,998
kWh
- - - - $2,000 $8,659
02 3.7214: Reduce or eliminate waste $56,000 $850 - - - - $56,000 - -
03 4.663: Level two – install control system using iiot devices with communication capabilities to store data to the cloud $30,696 $13,620 $4,547
88,633
kWh
- - - $10,800 - $15,349
04 2.3212: Optimize plant power factor $5,338 $7,581 - $5,338
-
kW-mo/yr
- - - - -
05 3.5111: Filter and reuse hydraulic oil $21,755 $80,000 - - $6,600
-
gal
$10,455 - $4,700 -
TOTAL RECOMMENDED $127,012 $102,051 $7,112
138,631
kWh
$5,338
-
kW-mo/yr
$6,600
-
gal
$10,455 $66,800 $6,700 $24,008
TOTAL IMPLEMENTED - - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs