| Assessment Year | 2023 |
|---|---|
| Principal Product | bread |
| NAICS | 311812: Commercial Bakeries |
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $50 M to 100M |
| # of Employees | 175 |
| Plant Area |
50,000
ft2
|
| Annual Production | 17,500,000
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $160,584 | 2,656,800 |
kWh
|
$0.060 | |
| Electricity Demand | $46,080 | 5,358 |
kW-mo/yr
|
$8.60 | |
| Electricity Fees | $23,303 | - |
|
- | |
| Natural Gas | $333,629 | 38,231 |
MMBtu
|
$8.73 | |
| Waste Disposal Costs | |||||
| Water Usage | $81,563 | 8,924 |
Tgal
|
$9.14 | |
| Solid Waste (non-haz) | $11,116 | 188,000 |
lb
|
$0.059 | |
| TOTAL YEARLY COSTS | $656,275 | ||||
| RECOMMENDED SAVINGS* | $54,580 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $29,713 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $18,535 | $8,125 |
$12,446
205,927
kWh
|
$6,089
-
kW-mo/yr
|
- | |
| 02 | 3.1194: Use automatic flow control | $24,867 | $9,600 |
$3,011
49,818
kWh
|
- |
$21,856
-
MMBtu
|
|
| 03 | 2.2441: Preheat boiler makeup water with waste process heat | $11,178 | $5,693 | - | - |
$11,178
-
MMBtu
|
|
| TOTAL RECOMMENDED | $54,580 | $23,418 |
$15,457
255,745
kWh
|
$6,089
-
kW-mo/yr
|
$33,034
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $29,713 | $13,818 |
$12,446
205,927
kWh
|
$6,089
-
kW-mo/yr
|
$11,178
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs