Assessment Year | 2022 |
---|---|
Principal Product | Aggregate Industry Equipment |
NAICS | 333120: Construction Machinery Manufacturing |
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
180,000
ft2
|
Annual Production | 310
units
|
Production Hrs. Annual | 5,916
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $189,522 | 2,614,097 |
kWh
|
$0.072 |
Electricity Demand | $41,954 | 7,221 |
kW-mo/yr
|
$5.81 |
Electricity Fees | $5,225 | - |
|
- |
Natural Gas | $28,109 | 4,432 |
MMBtu
|
$6.34 |
LPG | $47,231 | 1,471 |
MMBtu
|
$32.11 |
TOTAL YEARLY COSTS | $312,041 | |||
RECOMMENDED SAVINGS* | $146,969 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $146,969 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $6,763 | $1,880 |
$2,576
35,531
kWh
|
$4,187
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 3.5111: Filter and reuse hydraulic oil | $34,830 | $88,699 | - | - | - | - | - |
$31,784
-
gal
|
- | $3,000 |
$46
-
Tgal
|
|
03 | 2.3212: Optimize plant power factor | $3,913 | $10,533 | - | - | $3,913 | - | - | - | - | - | - | |
04 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $99,431 | $292,453 |
$(-7,204.0)
(-99,372)
kWh
|
- | - | - |
$47,231
-
MMBtu
|
- | $59,404 | - | - | |
05 | 2.2511: Insulate bare equipment | $2,032 | $9,520 | - | - | - |
$2,032
-
MMBtu
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $146,969 | $403,085 |
$(-4,628.0)
(-63,841)
kWh
|
$4,187
-
kW-mo/yr
|
$3,913 |
$2,032
-
MMBtu
|
$47,231
-
MMBtu
|
$31,784
-
gal
|
$59,404 | $3,000 |
$46
-
Tgal
|
||
TOTAL IMPLEMENTED | $146,969 | $403,085 |
$(-4,628.0)
(-63,841)
kWh
|
$4,187
-
kW-mo/yr
|
$3,913 |
$2,032
-
MMBtu
|
$47,231
-
MMBtu
|
$31,784
-
gal
|
$59,404 | $3,000 |
$46
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs