Assessment Year | 2021 |
---|---|
Principal Product | Semiconductor Products and Contract Manufacturing |
NAICS | 334413: Semiconductor and Related Device Manufacturing |
SIC | 3674: Semiconductors and Related Devices |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
170,000
ft2
|
Annual Production | 20,000
units
|
Production Hrs. Annual | 2,800
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $182,254 | 3,122,138 |
kWh
|
$0.058 | |
Electricity Demand | $46,933 | 7,097 |
kW-mo/yr
|
$6.61 | |
Electricity Fees | $63,157 | - |
|
- | |
Natural Gas | $30,875 | 3,442 |
MMBtu
|
$8.97 | |
Waste Disposal Costs | |||||
Solid Waste (non-haz) | $44,660 | 812,000 |
lb
|
$0.055 | |
TOTAL YEARLY COSTS | $367,879 | ||||
RECOMMENDED SAVINGS* | $98,069 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,176 | $40,448 |
$11,499
159,861
kWh
|
$3,962
-
kW-mo/yr
|
- | - | $1,150 | $(-435.0) | |
02 | 3.6192: Use a less expensive method of waste removal | $56,371 | - | - | - | - |
$56,371
-
lb
|
- | - | |
03 | 2.7234: Use heat pump for space conditioning | $25,522 | $19,860 |
$18,301
254,430
kWh
|
$16,502
-
kW-mo/yr
|
$(-9,281.0)
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $98,069 | $60,308 |
$29,800
414,291
kWh
|
$20,464
-
kW-mo/yr
|
$(-9,281.0)
-
MMBtu
|
$56,371
-
lb
|
$1,150 | $(-435.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs