ITAC Assessment: OR0721
ITAC logo
ITAC Assessment: OR0721
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Recyclable Materials
NAICS 562920: Materials Recovery Facilities
SIC 4953: Refuse Systems
Sales Range $5
M
to 10
M
# of Employees 160
Plant Area 190,000
ft2
Annual Production 32,561
ton
Production Hrs. Annual 3,120
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,653 1,147,400
kWh
Electricity Demand $19,614 4,471
kW-mo/yr
Electricity Fees $17,636 -
Natural Gas $13,236 1,576
MMBtu
Fuel Oil #2 $38,525 1,482
MMBtu
TOTAL YEARLY COSTS $155,664
RECOMMENDED SAVINGS* $58,237 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Personnel Changes Savings Primary Raw Material Savings
01 2.8227: Adjust / maintain fork lift trucks for most efficient operation $40,539 $84,752 $(-1,785.0)
(-34,320)
kWh
$(-5,610.0)
-
kW-mo/yr
$30,153
-
MMBtu
$17,781 -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $10,383 $7,807 $8,322
160,041
kWh
$1,742
-
kW-mo/yr
- $778 $(-459.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,615 $5,884 $4,668
71,538
kWh
$602
-
kW-mo/yr
- $332 $13
04 2.7423: Reduce heat gain by window tinting $1,700 $12,122 $1,700
26,048
kWh
- - - -
TOTAL RECOMMENDED $58,237 $110,565 $12,905
223,307
kWh
$(-3,266.0)
-
kW-mo/yr
$30,153
-
MMBtu
$18,891 $(-446.0)
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs