ITAC Assessment: OR0718
ITAC logo
ITAC Assessment: OR0718
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Flakeboard
NAICS 321219: Reconstituted Wood Product Manufacturing
SIC 2493: Reconstituted Wood Products
Sales Range $100
M
to 500
M
# of Employees 82
Plant Area 460,000
ft2
Annual Production 600
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,078,977 61,075,306
kWh
Electricity Demand $3,674 109,451
kW-mo/yr
Electricity Fees $668,171 -
Natural Gas $1,446,227 395,559
MMBtu
TOTAL YEARLY COSTS $5,197,049
RECOMMENDED SAVINGS* $139,585 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $84,306 $71,155 - $84,306
-
MMBtu
02 2.6212: Turn off equipment during breaks, reduce operating time $47,893 $5,142 $47,893
950,454
kWh
-
03 2.7311: Ventilation system to shut off when room is not in use $7,386 $27,337 $7,386
146,567
kWh
-
TOTAL RECOMMENDED $139,585 $103,634 $55,279
1,097,021
kWh
$84,306
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs