ITAC Assessment: OR0696
ITAC logo
ITAC Assessment: OR0696
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Beverages
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 90,000
ft2
Annual Production 110,000
bbl
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,640 1,698,600
kWh
Electricity Demand $47,923 4,219
kW-mo/yr
Natural Gas $39,510 6,049
MMBtu
Waste Disposal Costs
Water Usage $50,740 12,685
Tgal
Water Disposal $71,922 9,162
Tgal
TOTAL YEARLY COSTS $270,735
RECOMMENDED SAVINGS* $263,113 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Primary Product Savings
01 4.122: Develop standard procedures to improve internal yields $179,573 $3,044 - - - - - - $179,573
02 4.652: Replace existing equipment with more suitable substitutes $79,265 $37,275 - - $354
-
MMBtu
$265
-
Tgal
$521
-
Tgal
$78,125 -
03 2.1221: Replace obsolete burners with more efficient ones $2,365 $5,880 $591
14,023
kWh
- $1,774
-
MMBtu
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,910 $10,116 $987
23,400
kWh
$923
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $263,113 $56,315 $1,578
37,423
kWh
$923
-
kW-mo/yr
$2,128
-
MMBtu
$265
-
Tgal
$521
-
Tgal
$78,125 $179,573
TOTAL IMPLEMENTED - - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs