ITAC Assessment: OR0692
ITAC logo
ITAC Assessment: OR0692
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Fabricated Metal Structures
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $100
M
to 500
M
# of Employees 350
Plant Area 2,309,000
ft2
Annual Production 15
units
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $177,965 2,518,252
kWh
Electricity Demand $33,999 7,010
kW-mo/yr
Electricity Fees $10,856 -
TOTAL YEARLY COSTS $222,820
RECOMMENDED SAVINGS* $30,736 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Raw Material Savings One-time Revenue or Avoided Cost Savings
01 2.5123: Reduce fluid flow rates $26,801 $7,395 $26,801
379,236
kWh
- - -
02 2.2628: Utilize a less expensive cooling method $2,636 $3,060 $136
1,921
kWh
- - $2,500
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,299 $3,670 $700
9,899
kWh
$132
-
kW-mo/yr
$302 $165
TOTAL RECOMMENDED $30,736 $14,125 $27,637
391,056
kWh
$132
-
kW-mo/yr
$302 $2,665
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs