Assessment Year | 2017 |
---|---|
Principal Product | Automotive Batteries |
NAICS | 335911: Storage Battery Manufacturing |
SIC | 3691: Storage Batteries |
Sales Range | $1 M to 5M |
# of Employees | 250 |
Plant Area |
204,000
ft2
|
Annual Production | 5,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,608,531 | 30,255,314 |
kWh
|
$0.053 | |
Electricity Demand | $338,695 | 57,503 |
kW-mo/yr
|
$5.89 | |
Natural Gas | $200,099 | 41,266 |
MMBtu
|
$4.85 | |
Waste Disposal Costs | |||||
Water Usage | $20,564 | 10,255 |
Tgal
|
$2.01 | |
TOTAL YEARLY COSTS | $2,167,889 | ||||
RECOMMENDED SAVINGS* | $220,341 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | By-product Production Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1133: Adjust burners for efficient operation | $2,090 | $600 | - | - |
$2,090
-
MMBtu
|
- | - | - | - | - | - | |
02 | 2.7134: Use photocell controls | $2,967 | $2,000 |
$2,001
47,760
kWh
|
$204
-
kW-mo/yr
|
- | - | $232 | - | $530 | - | - | |
03 | 4.652: Replace existing equipment with more suitable substitutes | $205,629 | $340,000 |
$(-13,846.0)
(-328,882)
kWh
|
- | - | - | $2,550 | - | $6,000 | - | $210,925 | |
04 | 4.131: Modify process to reduce material use/cost | $3,195 | $5,650 | - | - |
$65
-
MMBtu
|
$3,208 | - | $3,564 | - | $(-3,642.0) | - | |
05 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $6,460 | $16,124 |
$6,460
153,443
kWh
|
- | - | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $220,341 | $364,374 |
$(-5,385.0)
(-127,679)
kWh
|
$204
-
kW-mo/yr
|
$2,155
-
MMBtu
|
$3,208 | $2,782 | $3,564 | $6,530 | $(-3,642.0) | $210,925 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs