Assessment Year | 2016 |
---|---|
Principal Product | Metal fabrication |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3441: Fabricated Structural Metal |
Sales Range | $50 M to 100M |
# of Employees | 25 |
Plant Area |
41,280
ft2
|
Annual Production | 1,000
units
|
Production Hrs. Annual | 2,860
hrs
|
Location (State) | Alaska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $98,836 | 679,680 |
kWh
|
$0.15 |
Electricity Demand | $20,636 | 3,270 |
kW-mo/yr
|
$6.31 |
Natural Gas | $38,948 | 4,863 |
MMBtu
|
$8.01 |
TOTAL YEARLY COSTS | $158,420 | |||
RECOMMENDED SAVINGS* | $20,775 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.2211: Use optimum temperature | $7,040 | - | - |
$7,040
-
MMBtu
|
- | |
02 | 3.1191: Change procedures / equipment / operating conditions | $12,375 | $2,995 | - | - | $12,375 | |
03 | 2.6218: Turn off equipment when not in use | $1,360 | $532 |
$1,360
9,351
kWh
|
- | - | |
TOTAL RECOMMENDED | $20,775 | $3,527 |
$1,360
9,351
kWh
|
$7,040
-
MMBtu
|
$12,375 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs