ITAC Assessment: OR0667
ITAC logo
ITAC Assessment: OR0667
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product soft wood product, timber, gutters, flooring,
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $50
M
to 100
M
# of Employees 120
Plant Area 1,263,240
ft2
Annual Production 40
units
Production Hrs. Annual 3,900
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $253,990 3,614,296
kWh
Electricity Demand $80,922 18,558
kW-mo/yr
Electricity Fees $33,074 -
Natural Gas $521,300 84,382
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,721 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,013

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.5123: Reduce fluid flow rates $18,192 $21,600 $18,192
248,353
kWh
- - -
02 2.2414: Use waste heat from hot flue gases to preheat $3,990 $8,335 - - $3,990
-
MMBtu
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,538 - $1,199
16,372
kWh
$339
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $15,475 $35,460 $12,769
174,314
kWh
$3,205
-
kW-mo/yr
- $(-499.0)
05 2.9114: Use solar heat to make electricty $9,526 $71,973 $9,332
127,400
kWh
$194
-
kW-mo/yr
- -
TOTAL RECOMMENDED $48,721 $137,368 $41,492
566,439
kWh
$3,738
-
kW-mo/yr
$3,990
-
MMBtu
$(-499.0)
TOTAL IMPLEMENTED $17,013 $35,460 $13,968
190,686
kWh
$3,544
-
kW-mo/yr
- $(-499.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs