| Assessment Year | 2016 |
|---|---|
| Principal Product | soft wood product, timber, gutters, flooring, |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $50 M to 100M |
| # of Employees | 120 |
| Plant Area |
1,263,240
ft2
|
| Annual Production | 40
units
|
| Production Hrs. Annual | 3,900
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $253,990 | 3,614,296 |
kWh
|
$0.070 |
| Electricity Demand | $80,922 | 18,558 |
kW-mo/yr
|
$4.36 |
| Electricity Fees | $33,074 | - |
|
- |
| Natural Gas | $521,300 | 84,382 |
MMBtu
|
$6.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $48,721 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,013 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.5123: Reduce fluid flow rates | $18,192 | $21,600 |
$18,192
248,353
kWh
|
- | - | - | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $3,990 | $8,335 | - | - |
$3,990
-
MMBtu
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,538 | - |
$1,199
16,372
kWh
|
$339
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,475 | $35,460 |
$12,769
174,314
kWh
|
$3,205
-
kW-mo/yr
|
- | $(-499.0) | |
| 05 | 2.9114: Use solar heat to make electricty | $9,526 | $71,973 |
$9,332
127,400
kWh
|
$194
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $48,721 | $137,368 |
$41,492
566,439
kWh
|
$3,738
-
kW-mo/yr
|
$3,990
-
MMBtu
|
$(-499.0) | ||
| TOTAL IMPLEMENTED | $17,013 | $35,460 |
$13,968
190,686
kWh
|
$3,544
-
kW-mo/yr
|
- | $(-499.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs