ITAC Assessment: OR0664
ITAC logo
ITAC Assessment: OR0664
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Hardboards
NAICS 321219: Reconstituted Wood Product Manufacturing
SIC 2493: Reconstituted Wood Products
Sales Range $5
M
to 10
M
# of Employees 191
Plant Area 2,744,280
ft2
Annual Production 1,400,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,758,138 31,061,180
kWh
Electricity Demand $232,961 72,540
kW-mo/yr
Electricity Fees $129,164 -
Wood $414,656 251,073
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,165 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,507

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.5121: Redesign flow to minimize mass transfer length $2,739 - $2,242
33,224
kWh
- - - $497 -
02 2.2511: Insulate bare equipment $1,310 $2,584 - - $1,310
-
MMBtu
- - -
03 2.7144: Install spectral reflectors / delamp $12,507 $32,393 $11,028
187,450
kWh
$1,193
-
kW-mo/yr
- $693 - $(-407.0)
04 2.4325: Upgrade conveyors $74,609 $242,718 $66,035
1,122,475
kWh
$8,574
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $91,165 $277,695 $79,305
1,343,149
kWh
$9,767
-
kW-mo/yr
$1,310
-
MMBtu
$693 $497 $(-407.0)
TOTAL IMPLEMENTED $12,507 $32,393 $11,028
187,450
kWh
$1,193
-
kW-mo/yr
- $693 - $(-407.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs