Assessment Year | 2015 |
---|---|
Principal Product | Dairy Products |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2022: Natural, Processed, and Imitation Cheese |
Sales Range | greater than $500 M |
# of Employees | 350 |
Plant Area |
339,010
ft2
|
Annual Production | 10,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,904,432 | 69,697,616 |
kWh
|
$0.042 |
Electricity Demand | $574,056 | 123,258 |
kW-mo/yr
|
$4.66 |
Electricity Fees | $18,600 | - |
|
- |
LPG | $10 | 1 |
MMBtu
|
$9.50 |
Other Energy | $593,657 | 32,805 |
MMBtu
|
$18.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,839,866 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,522,480 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Other Energy Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.652: Replace existing equipment with more suitable substitutes | $2,308,919 | $1,300,000 | - | - | - | - | - | - | $2,308,919 | |
02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $188,688 | $247,000 | - | - |
$188,688
-
MMBtu
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,591 | $27,789 |
$14,176
337,526
kWh
|
$2,202
-
kW-mo/yr
|
- | - | $509 | $704 | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $317,386 | - |
$1,577,843
38,112,145
kWh
|
- |
$(-1,882,768.0)
-
MMBtu
|
$622,311
-
MMBtu
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,282 | $22,500 |
$6,314
150,334
kWh
|
$968
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $2,839,866 | $1,597,289 |
$1,598,333
38,600,005
kWh
|
$3,170
-
kW-mo/yr
|
$(-1,694,080.0)
-
MMBtu
|
$622,311
-
MMBtu
|
$509 | $704 | $2,308,919 | ||
TOTAL IMPLEMENTED | $2,522,480 | $1,597,289 |
$20,490
487,860
kWh
|
$3,170
-
kW-mo/yr
|
$188,688
-
MMBtu
|
- | $509 | $704 | $2,308,919 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs