Assessment Year | 2015 |
---|---|
Principal Product | X-Ray Film |
NAICS | 325992: Photographic Film, Paper, Plate, and Chemical Manufacturing |
SIC | 3861: Photographic Equipment and Supplies |
Sales Range | $1 M to 5M |
# of Employees | 350 |
Plant Area |
237,000
ft2
|
Annual Production | 5,028
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,421,422 | 29,748,600 |
kWh
|
$0.048 |
Electricity Demand | $423,116 | 49,390 |
kW-mo/yr
|
$8.57 |
Electricity Fees | $71,308 | - |
|
- |
Natural Gas | $1,195,183 | 244,019 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $422,879 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $329,244 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6242: Minimize operation of equipment maintained in standby condition | $58,422 | $9,638 | - | - |
$58,422
-
MMBtu
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $270,822 | $210,050 |
$129,268
2,734,104
kWh
|
$36,529
-
kW-mo/yr
|
- | $105,025 | |
03 | 3.5311: Recover and reuse waste material | $93,635 | $132,280 | - | - |
$93,635
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $422,879 | $351,968 |
$129,268
2,734,104
kWh
|
$36,529
-
kW-mo/yr
|
$152,057
-
MMBtu
|
$105,025 | ||
TOTAL IMPLEMENTED | $329,244 | $219,688 |
$129,268
2,734,104
kWh
|
$36,529
-
kW-mo/yr
|
$58,422
-
MMBtu
|
$105,025 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs