Assessment Year | 2015 |
---|---|
Principal Product | abrasive slurry |
NAICS | 327910: Abrasive Product Manufacturing |
SIC | 3291: Abrasive Products |
Sales Range | $50 M to 100M |
# of Employees | 106 |
Plant Area |
126,500
ft2
|
Annual Production | 3,450
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $287,203 | 4,039,521 |
kWh
|
$0.071 |
Electricity Demand | $46,749 | 8,712 |
kW-mo/yr
|
$5.37 |
Electricity Fees | $15,145 | - |
|
- |
Natural Gas | $21,767 | 1,920 |
MMBtu
|
$11.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $72,548 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,340 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $18,604 | $16,250 |
$18,604
257,788
kWh
|
- | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,484 | $2,065 |
$5,497
76,174
kWh
|
$138
-
kW-mo/yr
|
- | $311 | - | $1,538 | |
03 | 2.6218: Turn off equipment when not in use | $2,825 | - |
$2,825
39,142
kWh
|
- | - | - | - | - | |
04 | 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating | $5,913 | $4,455 |
$15,476
214,438
kWh
|
- |
$(-9,563.0)
-
MMBtu
|
- | - | - | |
05 | 2.6218: Turn off equipment when not in use | $1,536 | $438 |
$790
10,948
kWh
|
- |
$746
-
MMBtu
|
- | - | - | |
06 | 2.9114: Use solar heat to make electricty | $23,387 | $10,298 |
$23,318
323,106
kWh
|
$69
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $572 | $1,000 |
$544
7,540
kWh
|
$28
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,277 | $2,139 |
$2,935
40,666
kWh
|
$342
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,638 | $1,819 |
$2,670
37,002
kWh
|
$(-32.0)
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.7135: Install occupancy sensors | $1,371 | $2,065 |
$1,090
15,109
kWh
|
- | - | - | $183 | $98 | |
11 | 2.2437: Recover waste heat from equipment | $4,941 | $19,500 | - | - |
$4,941
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $72,548 | $60,029 |
$73,749
1,021,913
kWh
|
$545
-
kW-mo/yr
|
$(-3,876.0)
-
MMBtu
|
$311 | $183 | $1,636 | ||
TOTAL IMPLEMENTED | $18,340 | $25,523 |
$11,102
153,842
kWh
|
$448
-
kW-mo/yr
|
$4,941
-
MMBtu
|
$311 | - | $1,538 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs