ITAC Assessment: OR0649
ITAC logo
ITAC Assessment: OR0649
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product abrasive slurry
NAICS 327910: Abrasive Product Manufacturing
SIC 3291: Abrasive Products
Sales Range $50
M
to 100
M
# of Employees 106
Plant Area 126,500
ft2
Annual Production 3,450
ton
Production Hrs. Annual 4,160
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $287,203 4,039,521
kWh
Electricity Demand $46,749 8,712
kW-mo/yr
Electricity Fees $15,145 -
Natural Gas $21,767 1,920
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,548 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,340

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $18,604 $16,250 $18,604
257,788
kWh
- - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,484 $2,065 $5,497
76,174
kWh
$138
-
kW-mo/yr
- $311 - $1,538
03 2.6218: Turn off equipment when not in use $2,825 - $2,825
39,142
kWh
- - - - -
04 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating $5,913 $4,455 $15,476
214,438
kWh
- $(-9,563.0)
-
MMBtu
- - -
05 2.6218: Turn off equipment when not in use $1,536 $438 $790
10,948
kWh
- $746
-
MMBtu
- - -
06 2.9114: Use solar heat to make electricty $23,387 $10,298 $23,318
323,106
kWh
$69
-
kW-mo/yr
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $572 $1,000 $544
7,540
kWh
$28
-
kW-mo/yr
- - - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,277 $2,139 $2,935
40,666
kWh
$342
-
kW-mo/yr
- - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,638 $1,819 $2,670
37,002
kWh
$(-32.0)
-
kW-mo/yr
- - - -
10 2.7135: Install occupancy sensors $1,371 $2,065 $1,090
15,109
kWh
- - - $183 $98
11 2.2437: Recover waste heat from equipment $4,941 $19,500 - - $4,941
-
MMBtu
- - -
TOTAL RECOMMENDED $72,548 $60,029 $73,749
1,021,913
kWh
$545
-
kW-mo/yr
$(-3,876.0)
-
MMBtu
$311 $183 $1,636
TOTAL IMPLEMENTED $18,340 $25,523 $11,102
153,842
kWh
$448
-
kW-mo/yr
$4,941
-
MMBtu
$311 - $1,538
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs