| Assessment Year | 2015 |
|---|---|
| Principal Product | Commercial heat treatment |
| NAICS | 332811: Metal Heat Treating |
| SIC | 3398: Metal Heat Treating |
| Sales Range | $100 M to 500M |
| # of Employees | 50 |
| Plant Area |
53,000
ft2
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $232,675 | 3,518,320 |
kWh
|
$0.066 |
| Electricity Demand | $33,623 | 11,756 |
kW-mo/yr
|
$2.86 |
| Electricity Fees | $56,824 | - |
|
- |
| Natural Gas | $308,050 | 47,951 |
MMBtu
|
$6.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $210,875 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $148,283 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1116: Improve combustion control capability | $80,430 | $5,071 | - | - |
$80,430
-
MMBtu
|
- | |
| 02 | 2.1116: Improve combustion control capability | $42,592 | $25,071 | - | - |
$42,592
-
MMBtu
|
- | |
| 03 | 4.131: Modify process to reduce material use/cost | $20,000 | $1,000 | - | - | - | $20,000 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $23,468 | $24,468 |
$20,885
333,120
kWh
|
$2,583
-
kW-mo/yr
|
- | - | |
| 05 | 2.2522: Isolate hot or cold equipment | $44,385 | $3,000 | - | - |
$44,385
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $210,875 | $58,610 |
$20,885
333,120
kWh
|
$2,583
-
kW-mo/yr
|
$167,407
-
MMBtu
|
$20,000 | ||
| TOTAL IMPLEMENTED | $148,283 | $32,539 |
$20,885
333,120
kWh
|
$2,583
-
kW-mo/yr
|
$124,815
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs