| Assessment Year | 2015 |
|---|---|
| Principal Product | Cast Steel |
| NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
| SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
| Sales Range | $100 M to 500M |
| # of Employees | 350 |
| Plant Area |
400,000
ft2
|
| Annual Production | 6,816
ton
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,071,800 | 22,519,200 |
kWh
|
$0.048 |
| Electricity Demand | $915,952 | 106,410 |
kW-mo/yr
|
$8.61 |
| Electricity Fees | $137,818 | - |
|
- |
| Natural Gas | $768,849 | 151,119 |
MMBtu
|
$5.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $246,897 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,100 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,697 | - |
$3,799
75,636
kWh
|
$1,898
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,403 | $46,360 |
$13,923
277,191
kWh
|
$4,738
-
kW-mo/yr
|
- | $1,690 | $4,052 | |
| 03 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $216,797 | $596,000 |
$206,542
4,111,917
kWh
|
$118,703
-
kW-mo/yr
|
$(-101,448.0)
-
MMBtu
|
$(-7,000.0) | - | |
| TOTAL RECOMMENDED | $246,897 | $642,360 |
$224,264
4,464,744
kWh
|
$125,339
-
kW-mo/yr
|
$(-101,448.0)
-
MMBtu
|
$(-5,310.0) | $4,052 | ||
| TOTAL IMPLEMENTED | $30,100 | $46,360 |
$17,722
352,827
kWh
|
$6,636
-
kW-mo/yr
|
- | $1,690 | $4,052 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs