ITAC Assessment: OR0643
ITAC logo
ITAC Assessment: OR0643
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Cast Steel
NAICS 331110: Iron and Steel Mills and Ferroalloy Manufacturing
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $100
M
to 500
M
# of Employees 350
Plant Area 400,000
ft2
Annual Production 6,816
ton
Production Hrs. Annual 4,160
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,071,800 22,519,200
kWh
Electricity Demand $915,952 106,410
kW-mo/yr
Electricity Fees $137,818 -
Natural Gas $768,849 151,119
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $246,897 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,100

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,697 - $3,799
75,636
kWh
$1,898
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $24,403 $46,360 $13,923
277,191
kWh
$4,738
-
kW-mo/yr
- $1,690 $4,052
03 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $216,797 $596,000 $206,542
4,111,917
kWh
$118,703
-
kW-mo/yr
$(-101,448.0)
-
MMBtu
$(-7,000.0) -
TOTAL RECOMMENDED $246,897 $642,360 $224,264
4,464,744
kWh
$125,339
-
kW-mo/yr
$(-101,448.0)
-
MMBtu
$(-5,310.0) $4,052
TOTAL IMPLEMENTED $30,100 $46,360 $17,722
352,827
kWh
$6,636
-
kW-mo/yr
- $1,690 $4,052
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs