Assessment Year | 2014 |
---|---|
Principal Product | Plywood |
NAICS | 321212: Softwood Veneer and Plywood Manufacturing |
SIC | 2493: Reconstituted Wood Products |
Sales Range | $100 M to 500M |
# of Employees | 390 |
Plant Area |
6,423,000
ft2
|
Annual Production | 316,955,697
thousand feet
|
Production Hrs. Annual | 8,712
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,532,514 | 31,884,000 |
kWh
|
$0.048 |
Electricity Demand | $507,220 | 119,779 |
kW-mo/yr
|
$4.23 |
Electricity Fees | $84,389 | - |
|
- |
Natural Gas | $45,799 | 5,923 |
MMBtu
|
$7.73 |
LPG | $30,194 | 1,824 |
MMBtu
|
$16.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $166,691 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $142,697 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $131,605 | $242,261 |
$104,903
2,081,399
kWh
|
$26,702
-
kW-mo/yr
|
- | |
02 | 2.4112: Install soft-start to eliminate nuisance trips | $2,455 | - |
$2,455
46,591
kWh
|
- | - | |
03 | 2.4112: Install soft-start to eliminate nuisance trips | $1,298 | $1,020 |
$1,298
25,955
kWh
|
- | - | |
04 | 2.1336: Install equipment to utilize waste fuel | $20,241 | $67,550 |
$(-8,835.0)
(-154,290)
kWh
|
$(-1,118.0)
-
kW-mo/yr
|
$30,194
-
MMBtu
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,092 | $12,092 |
$9,689
193,702
kWh
|
$1,403
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $166,691 | $322,923 |
$109,510
2,193,357
kWh
|
$26,987
-
kW-mo/yr
|
$30,194
-
MMBtu
|
||
TOTAL IMPLEMENTED | $142,697 | $254,353 |
$114,592
2,275,101
kWh
|
$28,105
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs