Assessment Year | 2013 |
---|---|
Principal Product | Pellets |
NAICS | 333131: Mining Machinery and Equipment Manufacturing |
SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
Sales Range | $5 M to 10M |
# of Employees | 6 |
Plant Area |
290,000
ft2
|
Annual Production | 31,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $85,840 | 1,645,520 |
kWh
|
$0.052 |
Electricity Demand | $38,435 | 5,043 |
kW-mo/yr
|
$7.62 |
Electricity Fees | $10,419 | - |
|
- |
Natural Gas | $167,483 | 29,268 |
MMBtu
|
$5.72 |
LPG | $7,200 | 306 |
MMBtu
|
$23.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $280,868 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $139,478 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Wood Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.132: Purchase new equipment to reduce material use / cost | $32,340 | - | - | - | - | - | - | $840 | - | - | $31,500 | |
02 | 4.111: Add equipment/ operators to reduce production bottleneck | $107,138 | $55,641 |
$38
713
kWh
|
- | - | - | - | $107,100 | - | - | - | |
03 | 4.114: Add/modify equipment to improve drying process | $125,546 | $300,000 |
$2,502
47,113
kWh
|
- |
$114,208
-
MMBtu
|
- |
$(-52,316.0)
-
MMBtu
|
$61,152 | - | - | - | |
04 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $11,970 | $41,000 |
$(-1,492.0)
(-28,100)
kWh
|
$(-2,513.0)
-
kW-mo/yr
|
- |
$7,200
-
MMBtu
|
- | - | $8,775 | - | - | |
05 | 2.2511: Insulate bare equipment | $518 | $135 | - | - |
$518
-
MMBtu
|
- | - | - | - | - | - | |
06 | 2.7273: Install desiccant humidity control system | $2,698 | $1,220 | - | - |
$2,698
-
MMBtu
|
- | - | - | - | - | - | |
07 | 2.7134: Use photocell controls | $658 | $966 |
$464
8,738
kWh
|
- | - | - | - | - | $37 | $157 | - | |
TOTAL RECOMMENDED | $280,868 | $398,962 |
$1,512
28,464
kWh
|
$(-2,513.0)
-
kW-mo/yr
|
$117,424
-
MMBtu
|
$7,200
-
MMBtu
|
$(-52,316.0)
-
MMBtu
|
$169,092 | $8,812 | $157 | $31,500 | ||
TOTAL IMPLEMENTED | $139,478 | $55,641 |
$38
713
kWh
|
- | - | - | - | $107,940 | - | - | $31,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Wood Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs