Assessment Year | 2012 |
---|---|
Principal Product | Drywall Corner Trims |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
55,000
ft2
|
Annual Production | 4,320,000
units
|
Production Hrs. Annual | 1,800
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,717 | 1,707,000 |
kWh
|
$0.057 |
Electricity Demand | $44,130 | 6,617 |
kW-mo/yr
|
$6.67 |
Electricity Fees | $10,909 | - |
|
- |
Natural Gas | $3,562 | 388 |
MMBtu
|
$9.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,144 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,865 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2628: Utilize a less expensive cooling method | $14,559 | $2,500 |
$11,012
187,814
kWh
|
$3,547
-
kW-mo/yr
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,704 | $500 |
$943
16,087
kWh
|
$761
-
kW-mo/yr
|
- | - | - | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $334 | - |
$334
5,688
kWh
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $940 | $392 |
$565
9,640
kWh
|
$375
-
kW-mo/yr
|
- | - | - | |
05 | 4.622: Install rotating carousels to reduce set-up times | $4,720 | - |
$(-334.0)
(-5,702)
kWh
|
- | - | - | $5,054 | |
06 | 2.2223: Enhance sensitivity of temperature control and cutoff | $6,653 | $385 | - | - | - | - | $6,653 | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,399 | $560 |
$5,299
90,381
kWh
|
- | $(-3,900.0) | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,835 | $2,724 |
$3,694
63,013
kWh
|
$531
-
kW-mo/yr
|
$146 | $464 | - | |
TOTAL RECOMMENDED | $35,144 | $7,061 |
$21,513
366,921
kWh
|
$5,214
-
kW-mo/yr
|
$(-3,754.0) | $464 | $11,707 | ||
TOTAL IMPLEMENTED | $15,865 | $4,561 |
$10,835
184,809
kWh
|
$1,667
-
kW-mo/yr
|
$(-3,754.0) | $464 | $6,653 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs