Assessment Year | 2012 |
---|---|
Principal Product | Canned Goods |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $5 M to 10M |
# of Employees | 475 |
Plant Area |
610,000
ft2
|
Annual Production | 18,500
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $289,785 | 6,075,210 |
kWh
|
$0.048 |
Electricity Demand | $118,122 | 17,448 |
kW-mo/yr
|
$6.77 |
Natural Gas | $547,146 | 97,150 |
MMBtu
|
$5.63 |
LPG | $31,920 | 1,522 |
MMBtu
|
$20.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $128,870 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $6,320 | - |
$3,781
72,633
kWh
|
$2,539
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.2121: Increase amount of condensate returned | $26,558 | $19,925 | - | - |
$21,084
-
MMBtu
|
- | - | - |
$5,474
-
Tgal
|
|
03 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $16,839 | $29,000 |
$(-4,547.0)
(-87,360)
kWh
|
$(-11,374.0)
-
kW-mo/yr
|
- |
$20,160
-
MMBtu
|
$12,600 | - | - | |
04 | 2.4322: Use or replace with energy efficient substitutes | $12,631 | $27,000 |
$12,631
242,665
kWh
|
- | - | - | - | - | - | |
05 | 3.4151: Minimize water usage | $4,574 | $7,000 | - | - | - | - | - | - |
$4,574
-
Tgal
|
|
06 | 2.2444: Use hot process fluids to preheat incoming process fluids | $7,796 | $19,701 | - | - |
$7,796
-
MMBtu
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $54,152 | $251,677 |
$38,013
730,325
kWh
|
$10,318
-
kW-mo/yr
|
- | - | $323 | $5,498 | - | |
TOTAL RECOMMENDED | $128,870 | $354,303 |
$49,878
958,263
kWh
|
$1,483
-
kW-mo/yr
|
$28,880
-
MMBtu
|
$20,160
-
MMBtu
|
$12,923 | $5,498 |
$10,048
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs