Assessment Year | 2009 |
---|---|
Principal Product | Bread and Buns |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
124,500
ft2
|
Annual Production | 52,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $232,725 | 6,853,200 |
kWh
|
$0.034 |
Electricity Demand | $70,691 | 11,852 |
kW-mo/yr
|
$5.96 |
Natural Gas | $584,556 | 56,126 |
MMBtu
|
$10.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,952 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,000 | $350 | - | - |
$7,000
-
MMBtu
|
- | - | |
02 | 2.1113: Reduce combustion air flow to optimum | $24,190 | $17,000 | - | - |
$24,190
-
MMBtu
|
- | - | |
03 | 2.3212: Optimize plant power factor | $7,200 | $10,500 | - |
$7,200
-
kW-mo/yr
|
- | - | - | |
04 | 2.7135: Install occupancy sensors | $4,087 | $7,170 |
$2,461
74,868
kWh
|
- | - | - | $1,626 | |
05 | 3.1291: Eliminate practice of mixing waste streams | $3,220 | $6,680 | - | - | - |
$3,220
-
lb
|
- | |
06 | 2.4133: Use most efficient type of electric motors | $14,466 | $37,682 |
$11,501
349,478
kWh
|
$2,965
-
kW-mo/yr
|
- | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,406 | $1,600 |
$1,116
33,908
kWh
|
$290
-
kW-mo/yr
|
- | - | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $2,132 | $13,620 |
$2,132
89,577
kWh
|
- | - | - | - | |
09 | 2.2136: Install / repair insulation on steam lines | $3,251 | $1,456 | - | - |
$3,251
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $66,952 | $96,058 |
$17,210
547,831
kWh
|
$10,455
-
kW-mo/yr
|
$34,441
-
MMBtu
|
$3,220
-
lb
|
$1,626 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs