| Assessment Year | 2008 |
|---|---|
| Principal Product | Steel building components |
| NAICS | 332311: Prefabricated Metal Building and Component Manufacturing |
| SIC | 3448: Prefabricated Metal Buildings and Components |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
140,000
ft2
|
| Annual Production | 40
pieces
|
| Production Hrs. Annual | 4,450
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $105,835 | 1,612,600 |
kWh
|
$0.066 |
| Electricity Demand | $14,550 | 5,450 |
kW-mo/yr
|
$2.67 |
| Electricity Fees | $10,490 | - |
|
- |
| Natural Gas | $82,911 | 7,571 |
MMBtu
|
$10.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $154,596 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.911: Solar | $112,205 | $783,772 |
$112,205
1,522,800
kWh
|
- | - | |
| 02 | 3.212: Painting operations | $31,122 | $1,120 | - | - |
$31,122
-
gal
|
|
| 03 | 2.2437: Recover waste heat from equipment | $3,350 | $385 | - |
$3,350
-
MMBtu
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $3,260 | $6,902 |
$3,260
40,506
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,132 | $9,045 |
$3,132
36,691
kWh
|
- | - | |
| 06 | 2.6218: Turn off equipment when not in use | $1,527 | - |
$1,527
21,942
kWh
|
- | - | |
| TOTAL RECOMMENDED | $154,596 | $801,224 |
$120,124
1,621,939
kWh
|
$3,350
-
MMBtu
|
$31,122
-
gal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs