ITAC Assessment: OR0527
ITAC logo
ITAC Assessment: OR0527
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Window Fixtures
NAICS 332321: Metal Window and Door Manufacturing
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $50
M
to 100
M
# of Employees 217
Plant Area 120,000
ft2
Annual Production 20,000
pieces
Production Hrs. Annual 5,780
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,258 2,984,400
kWh
Electricity Demand $40,276 585
kW-mo/yr
Natural Gas $47,851 38,450
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $132,970 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,270

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Increase in Production Savings
01 -.----: $102,600 $32,700 - - - - $102,600
02 -.----: $12,200 $77,700 - - $4,600
-
MMBtu
- $7,600
03 -.----: $6,900 $1,400 $5,950
95,280
kWh
$950
-
kW-mo/yr
- - -
04 -.----: $3,900 $90 $3,900
63,200
kWh
- - - -
05 -.----: $3,770 $3,770 $3,770
61,440
kWh
- - - -
06 -.----: $3,600 - - - - $3,600 -
TOTAL RECOMMENDED $132,970 $115,660 $13,620
219,920
kWh
$950
-
kW-mo/yr
$4,600
-
MMBtu
$3,600 $110,200
TOTAL IMPLEMENTED $11,270 $3,860 $7,670
124,640
kWh
- - $3,600 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs