| Assessment Year | 2008 |
|---|---|
| Principal Product | Window Fixtures |
| NAICS | 332321: Metal Window and Door Manufacturing |
| SIC | 3231: Glass Products, Made of Purchased Glass |
| Sales Range | $50 M to 100M |
| # of Employees | 217 |
| Plant Area |
120,000
ft2
|
| Annual Production | 20,000
pieces
|
| Production Hrs. Annual | 5,780
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $180,258 | 2,984,400 |
kWh
|
$0.060 |
| Electricity Demand | $40,276 | 585 |
kW-mo/yr
|
$68.85 |
| Natural Gas | $47,851 | 38,450 |
MMBtu
|
$1.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $132,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,270 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | -.----: | $102,600 | $32,700 | - | - | - | - | $102,600 | |
| 02 | -.----: | $12,200 | $77,700 | - | - |
$4,600
-
MMBtu
|
- | $7,600 | |
| 03 | -.----: | $6,900 | $1,400 |
$5,950
95,280
kWh
|
$950
-
kW-mo/yr
|
- | - | - | |
| 04 | -.----: | $3,900 | $90 |
$3,900
63,200
kWh
|
- | - | - | - | |
| 05 | -.----: | $3,770 | $3,770 |
$3,770
61,440
kWh
|
- | - | - | - | |
| 06 | -.----: | $3,600 | - | - | - | - | $3,600 | - | |
| TOTAL RECOMMENDED | $132,970 | $115,660 |
$13,620
219,920
kWh
|
$950
-
kW-mo/yr
|
$4,600
-
MMBtu
|
$3,600 | $110,200 | ||
| TOTAL IMPLEMENTED | $11,270 | $3,860 |
$7,670
124,640
kWh
|
- | - | $3,600 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs