Assessment Year | 2008 |
---|---|
Principal Product | Window Fixtures |
NAICS | 332321: Metal Window and Door Manufacturing |
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $50 M to 100M |
# of Employees | 217 |
Plant Area |
120,000
ft2
|
Annual Production | 20,000
pieces
|
Production Hrs. Annual | 5,780
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $180,258 | 2,984,400 |
kWh
|
$0.060 |
Electricity Demand | $40,276 | 585 |
kW-mo/yr
|
$68.85 |
Natural Gas | $47,851 | 38,450 |
MMBtu
|
$1.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $132,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,270 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | -.----: | $102,600 | $32,700 | - | - | - | - | $102,600 | |
02 | -.----: | $12,200 | $77,700 | - | - |
$4,600
-
MMBtu
|
- | $7,600 | |
03 | -.----: | $6,900 | $1,400 |
$5,950
95,280
kWh
|
$950
-
kW-mo/yr
|
- | - | - | |
04 | -.----: | $3,900 | $90 |
$3,900
63,200
kWh
|
- | - | - | - | |
05 | -.----: | $3,770 | $3,770 |
$3,770
61,440
kWh
|
- | - | - | - | |
06 | -.----: | $3,600 | - | - | - | - | $3,600 | - | |
TOTAL RECOMMENDED | $132,970 | $115,660 |
$13,620
219,920
kWh
|
$950
-
kW-mo/yr
|
$4,600
-
MMBtu
|
$3,600 | $110,200 | ||
TOTAL IMPLEMENTED | $11,270 | $3,860 |
$7,670
124,640
kWh
|
- | - | $3,600 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs