Assessment Year | 2007 |
---|---|
Principal Product | fruit and candy |
NAICS | 311352: Confectionery Manufacturing from Purchased Chocolate |
SIC | 2064: Candy and Other Confectionery Products |
Sales Range | $5 M to 10M |
# of Employees | 500 |
Plant Area |
50,000
ft2
|
Annual Production | 500,000
lb
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,273,652 | 28,350,000 |
kWh
|
$0.045 |
Electricity Demand | $214,229 | 90,000 |
kW-mo/yr
|
$2.38 |
Natural Gas | $512,036 | 54,857 |
MMBtu
|
$9.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $82,400 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $82,400 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $33,600 | $32,500 | - | - | $33,600 | |
02 | 2.329: | $15,400 | - |
$15,400
418,300
kWh
|
- | - | |
03 | 2.7135: Install occupancy sensors | $11,700 | $31,650 |
$11,700
195,700
kWh
|
- | - | |
04 | 2.7135: Install occupancy sensors | $8,600 | $17,550 |
$8,600
171,500
kWh
|
- | - | |
05 | 2.2127: Flash condensate to produce lower pressure steam | $4,800 | $6,400 | - |
$4,800
-
MMBtu
|
- | |
06 | 2.1224: Replace boiler | $4,900 | $5,250 | - |
$4,900
-
MMBtu
|
- | |
07 | 2.2123: Insulate feedwater tank | $3,400 | $2,160 | - |
$3,400
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $82,400 | $95,510 |
$35,700
785,500
kWh
|
$13,100
-
MMBtu
|
$33,600 | ||
TOTAL IMPLEMENTED | $82,400 | $95,510 |
$35,700
785,500
kWh
|
$13,100
-
MMBtu
|
$33,600 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs