| Assessment Year | 2006 |
|---|---|
| Principal Product | Fruit Puree |
| NAICS | 311422: Specialty Canning |
| SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
| Sales Range | $10 M to 50M |
| # of Employees | 290 |
| Plant Area |
653,400
ft2
|
| Annual Production | 80,000
ton
|
| Production Hrs. Annual | 6,336
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $154,590 | 7,987,180 |
kWh
|
$0.019 |
| Electricity Demand | $50,081 | 11,180 |
kW-mo/yr
|
$4.48 |
| Natural Gas | $2,091,106 | 204,269 |
MMBtu
|
$10.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $186,121 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $157,941 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $37,500 | $42,500 |
$(-6,500.0)
(-180,000)
kWh
|
$(-1,100.0)
-
kW-mo/yr
|
- |
$29,500
-
MMBtu
|
$15,600
-
Tgal
|
- | - | |
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $23,480 | $24,300 |
$(-23,330.0)
(-679,460)
kWh
|
$(-4,080.0)
-
kW-mo/yr
|
- |
$30,890
-
MMBtu
|
- | - | $20,000 | |
| 03 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $17,800 | $36,000 |
$4,900
140,700
kWh
|
$1,900
-
kW-mo/yr
|
- | - | - |
$11,000
-
gal
|
- | |
| 04 | 4.431: Train operators for maximum operating efficiency | $50,800 | $11,300 | - | - | - | - | - | - | $50,800 | |
| 05 | 3.7122: Maximize production runs to reduce cleaning | $46,500 | - | - | - | - | - | - | - | $46,500 | |
| 06 | 2.2136: Install / repair insulation on steam lines | $5,341 | $600 | - | - | - |
$5,341
-
MMBtu
|
- | - | - | |
| 07 | 2.3212: Optimize plant power factor | $4,700 | $18,300 | - | - | $4,700 | - | - | - | - | |
| TOTAL RECOMMENDED | $186,121 | $133,000 |
$(-24,930.0)
(-718,760)
kWh
|
$(-3,280.0)
-
kW-mo/yr
|
$4,700 |
$65,731
-
MMBtu
|
$15,600
-
Tgal
|
$11,000
-
gal
|
$117,300 | ||
| TOTAL IMPLEMENTED | $157,941 | $90,400 |
$(-1,600.0)
(-39,300)
kWh
|
$800
-
kW-mo/yr
|
- |
$34,841
-
MMBtu
|
$15,600
-
Tgal
|
$11,000
-
gal
|
$97,300 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs