| Assessment Year | 2004 |
|---|---|
| Principal Product | Hydraulic Cylinders |
| NAICS | 333995: Fluid Power Cylinder and Actuator Manufacturing |
| SIC | 3593: Fluid Power Cylinders and Actuators |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
80,000
ft2
|
| Annual Production | 18,000
pieces
|
| Production Hrs. Annual | 7,344
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $76,510 | 1,759,308 |
kWh
|
$0.043 |
| Electricity Demand | $20,863 | 55,308 |
kW-mo/yr
|
$0.38 |
| Electricity Fees | $1,590 | - |
|
- |
| Natural Gas | $18,892 | 2,241 |
MMBtu
|
$8.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $117,202 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,185 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.111: Add equipment/ operators to reduce production bottleneck | $92,000 | $1,200 | - | - | - | $(-34,000.0) | - | - | $126,000 | |
| 02 | 4.425: Eliminate/reduce redundant inspections | $11,400 | $2,800 | - | - | - | - | $11,400 | - | - | |
| 03 | 3.1161: Eliminate/reduce an operation | $9,627 | $250 |
$4,260
99,000
kWh
|
$5,367
-
MMBtu
|
- | - | - | - | - | |
| 04 | 3.1191: Change procedures / equipment / operating conditions | $2,990 | $300 |
$2,400
55,500
kWh
|
- |
$350
-
Tgal
|
- | - |
$240
-
Tgal
|
- | |
| 05 | 3.1161: Eliminate/reduce an operation | $1,185 | $165 |
$1,185
28,140
kWh
|
- | - | - | - | - | - | |
| TOTAL RECOMMENDED | $117,202 | $4,715 |
$7,845
182,640
kWh
|
$5,367
-
MMBtu
|
$350
-
Tgal
|
$(-34,000.0) | $11,400 |
$240
-
Tgal
|
$126,000 | ||
| TOTAL IMPLEMENTED | $1,185 | $165 |
$1,185
28,140
kWh
|
- | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs