ITAC Assessment: OR0470
ITAC logo
ITAC Assessment: OR0470
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Hydraulic Cylinders
NAICS 333995: Fluid Power Cylinder and Actuator Manufacturing
SIC 3593: Fluid Power Cylinders and Actuators
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 80,000
ft2
Annual Production 18,000
pieces
Production Hrs. Annual 7,344
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $76,510 1,759,308
kWh
Electricity Demand $20,863 55,308
kW-mo/yr
Electricity Fees $1,590 -
Natural Gas $18,892 2,241
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $117,202 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,185

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $92,000 $1,200 - - - $(-34,000.0) - - $126,000
02 4.425: Eliminate/reduce redundant inspections $11,400 $2,800 - - - - $11,400 - -
03 3.1161: Eliminate/reduce an operation $9,627 $250 $4,260
99,000
kWh
$5,367
-
MMBtu
- - - - -
04 3.1191: Change procedures / equipment / operating conditions $2,990 $300 $2,400
55,500
kWh
- $350
-
Tgal
- - $240
-
Tgal
-
05 3.1161: Eliminate/reduce an operation $1,185 $165 $1,185
28,140
kWh
- - - - - -
TOTAL RECOMMENDED $117,202 $4,715 $7,845
182,640
kWh
$5,367
-
MMBtu
$350
-
Tgal
$(-34,000.0) $11,400 $240
-
Tgal
$126,000
TOTAL IMPLEMENTED $1,185 $165 $1,185
28,140
kWh
- - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs