Assessment Year | 2004 |
---|---|
Principal Product | Ion Guns |
NAICS | 334516: Analytical Laboratory Instrument Manufacturing |
SIC | 3826: Laboratory Analytical Instruments |
Sales Range | $100 M to 500M |
# of Employees | 380 |
Plant Area |
180,000
ft2
|
Annual Production | 36
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $411,223 | 8,186,800 |
kWh
|
$0.050 |
Electricity Demand | $73,093 | 14,530 |
kW-mo/yr
|
$5.03 |
Electricity Fees | $18,655 | - |
|
- |
Natural Gas | $12,256 | 1,398 |
MMBtu
|
$8.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,682,130 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,377,220 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,372,930 | $1,150 | - | - | $(-27,070.0) | - | $2,400,000 | |
02 | 4.652: Replace existing equipment with more suitable substitutes | $303,000 | $1,000 | - | - | - | $(-180,000.0) | $483,000 | |
03 | 2.6218: Turn off equipment when not in use | $4,290 | $2,690 |
$3,640
72,550
kWh
|
$650
-
kW-mo/yr
|
- | - | - | |
04 | 2.7135: Install occupancy sensors | $1,910 | $875 |
$1,910
38,100
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $2,682,130 | $5,715 |
$5,550
110,650
kWh
|
$650
-
kW-mo/yr
|
$(-27,070.0) | $(-180,000.0) | $2,883,000 | ||
TOTAL IMPLEMENTED | $2,377,220 | $3,840 |
$3,640
72,550
kWh
|
$650
-
kW-mo/yr
|
$(-27,070.0) | - | $2,400,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs