ITAC Assessment: OR0454
ITAC logo
ITAC Assessment: OR0454
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Gun Swivels
NAICS 332510: Hardware Manufacturing
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 25
Plant Area
n/a
Annual Production 7,600,000
pieces
Production Hrs. Annual 1,912
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $33,755 656,320
kWh
Electricity Demand $9,851 2,125
kW-mo/yr
Electricity Fees $1,873 -
Natural Gas $23,100 2,826
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $87,120 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,660

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.5194: Redesign process $39,560 - - $3,420
-
MMBtu
- $31,600 $4,540
02 4.126: Install sensors to detect defects $24,900 $2,600 - - - - $24,900
03 4.322: Eliminate old stock and modify inventory control $5,720 $13,080 - - $5,720 - -
04 3.8134: Use water-based cutting fluids to eliminate need for solvent cleaning $16,940 $29,200 $(-2,260.0)
(-42,250)
kWh
- - $19,200 -
TOTAL RECOMMENDED $87,120 $44,880 $(-2,260.0)
(-42,250)
kWh
$3,420
-
MMBtu
$5,720 $50,800 $29,440
TOTAL IMPLEMENTED $22,660 $42,280 $(-2,260.0)
(-42,250)
kWh
- $5,720 $19,200 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs