| Assessment Year | 2003 |
|---|---|
| Principal Product | Frozen Onions, Peppers |
| NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
| SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
27,520
ft2
|
| Annual Production | 62,900,000
lb
|
| Production Hrs. Annual | 8,211
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $453,824 | 11,793,346 |
kWh
|
$0.038 |
| Electricity Demand | $61,811 | 23,328 |
kW-mo/yr
|
$2.65 |
| Electricity Fees | $30,560 | - |
|
- |
| Natural Gas | $140,358 | 25,498 |
MMBtu
|
$5.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,896,665 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,877,400 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,842,800 | $348,000 |
$(-37,200.0)
(-1,279,500)
kWh
|
- | - | $(-187,000.0) | $(-1,163,000.0) | $3,230,000 | |
| 02 | 4.423: Move product using mechanical means | $15,000 | $75 | - | - | - | $15,000 | - | - | |
| 03 | 2.2621: Modify refrigeration system to operate at a lower pressure | $16,500 | $5,130 |
$16,500
567,000
kWh
|
- | - | - | - | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,500 | - |
$3,000
103,000
kWh
|
$500
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.1231: Establish burner maintenance schedule for boilers | $2,600 | $700 | - | - |
$2,600
-
MMBtu
|
- | - | - | |
| 06 | 2.7132: Install timers on light switches in little used areas | $765 | $1,300 |
$765
26,080
kWh
|
- | - | - | - | - | |
| 07 | 2.4133: Use most efficient type of electric motors | $15,500 | $38,200 |
$12,600
427,000
kWh
|
$2,900
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $1,896,665 | $393,405 |
$(-4,335.0)
(-156,420)
kWh
|
$3,400
-
kW-mo/yr
|
$2,600
-
MMBtu
|
$(-172,000.0) | $(-1,163,000.0) | $3,230,000 | ||
| TOTAL IMPLEMENTED | $1,877,400 | $392,030 |
$(-8,100.0)
(-285,500)
kWh
|
$2,900
-
kW-mo/yr
|
$2,600
-
MMBtu
|
$(-187,000.0) | $(-1,163,000.0) | $3,230,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs