Assessment Year | 2003 |
---|---|
Principal Product | green dimensional lumber |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
40,000
ft2
|
Annual Production | 17,524,500
units
|
Production Hrs. Annual | 1,960
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,202 | 1,481,000 |
kWh
|
$0.042 |
Electricity Demand | $54,965 | 10,410 |
kW-mo/yr
|
$5.28 |
Electricity Fees | $5,136 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $220,245 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $132,250 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Raw Material Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.131: Modify process to reduce material use/cost | $117,000 | $150,300 | - | - | $117,000 | - | |
02 | 4.131: Modify process to reduce material use/cost | $78,000 | $62,900 | n/a | - | - | - | $78,000 |
03 | 2.3134: Shift from daytime to nighttime operation | $9,500 | - | - |
$9,500
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,080 | $3,000 |
$2,160
51,600
kWh
|
$920
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,780 | $15,000 |
$4,670
111,160
kWh
|
$3,110
-
kW-mo/yr
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $4,390 | $10,800 |
$2,330
55,300
kWh
|
$2,060
-
kW-mo/yr
|
- | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $495 | - |
$265
2,380
kWh
|
$230
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $220,245 | $242,000 |
$9,425
220,440
kWh
|
$15,820
-
kW-mo/yr
|
$117,000 | $78,000 | ||
TOTAL IMPLEMENTED | $132,250 | $179,100 |
$9,160
218,060
kWh
|
$6,090
-
kW-mo/yr
|
$117,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Primary Raw Material Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs