Assessment Year | 2002 |
---|---|
Principal Product | 2 |
NAICS |
n/a
|
SIC | 1041: Gold Ores |
Sales Range | $100 M to 500M |
# of Employees | 1,462 |
Plant Area |
n/a
|
Annual Production | 0
lb
|
Production Hrs. Annual | 8,565
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $17,414,720 | 353,469,361 |
kWh
|
$0.049 |
Electricity Demand | $216,146 | 518,750 |
kW-mo/yr
|
$0.42 |
Electricity Fees | $6,000 | - |
|
- |
Natural Gas | $2,151,480 | 778,171 |
MMBtu
|
$2.76 |
LPG | $3,377,411 | 594,294 |
MMBtu
|
$5.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,957,209 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $103,131 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1117: Relocate oven / furnace to more efficient location | $577,590 | $207,147 | n/a | - | - |
$577,590
-
MMBtu
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $958,574 | $1,727,000 |
$819,644
16,234,542
kWh
|
$138,930
-
kW-mo/yr
|
- | |
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $158,150 | $118,500 | n/a | - | - |
$158,150
-
MMBtu
|
04 | 2.4133: Use most efficient type of electric motors | $119,700 | $241,870 |
$104,000
2,105,788
kWh
|
$15,700
-
kW-mo/yr
|
- | |
05 | 4.111: Add equipment/ operators to reduce production bottleneck | $69,350 | $46,000 |
$60,810
1,246,590
kWh
|
$8,540
-
kW-mo/yr
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $25,349 | - |
$22,029
446,197
kWh
|
$3,320
-
kW-mo/yr
|
- | |
07 | 2.1133: Adjust burners for efficient operation | $20,311 | $1,000 | - | - |
$20,311
-
MMBtu
|
|
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,470 | $12,200 |
$12,190
260,250
kWh
|
$1,280
-
kW-mo/yr
|
- | |
09 | 4.111: Add equipment/ operators to reduce production bottleneck | $14,715 | $45,000 | - | - |
$14,715
-
MMBtu
|
|
TOTAL RECOMMENDED | $1,957,209 | $2,398,717 |
$1,018,673
20,293,367
kWh
|
$167,770
-
kW-mo/yr
|
$770,766
-
MMBtu
|
||
TOTAL IMPLEMENTED | $103,131 | $59,200 |
$73,000
1,506,840
kWh
|
$9,820
-
kW-mo/yr
|
$20,311
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs