Assessment Year | 2002 |
---|---|
Principal Product | camping trailers |
NAICS |
n/a
|
SIC | 3792: Travel Trailers and Campers |
Sales Range | $1 M to 5M |
# of Employees | 24 |
Plant Area |
19,000
ft2
|
Annual Production | 300
pieces
|
Production Hrs. Annual | 2,442
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $4,050 | 69,820 |
kWh
|
$0.058 |
Electricity Demand | $488 | 336 |
kW-mo/yr
|
$1.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,620,420 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $214,220 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.511: Expand operations into unused space | $10,000 | $1,200 | - | - | - | - | - | $10,000 | |
02 | 4.432: Cross-train personnel to avoid lost time | $214,000 | $5,000 | - | - | - | - | - | $214,000 | |
03 | 4.431: Train operators for maximum operating efficiency | $142,400 | $25,000 | n/a | - | - | - | - | $142,400 | - |
04 | 4.423: Move product using mechanical means | $3,500 | $2,800 | - | - | - | - | $3,500 | - | |
05 | 4.426: Modify workload | $1,250,300 | $29,300 | n/a | - | - | $78,200 | $689,200 | - | $482,900 |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $220 | $50 |
$50
1,036
kWh
|
$170
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,620,420 | $63,350 |
$50
1,036
kWh
|
$170
-
kW-mo/yr
|
$78,200 | $689,200 | $145,900 | $706,900 | ||
TOTAL IMPLEMENTED | $214,220 | $5,050 |
$50
1,036
kWh
|
$170
-
kW-mo/yr
|
- | - | - | $214,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs