Assessment Year | 2022 |
---|---|
Principal Product | Machining |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
22,500
ft2
|
Annual Production | 125,500
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $41,706 | 1,062,581 |
kWh
|
$0.039 | |
Electricity Demand | $17,162 | 2,349 |
kW-mo/yr
|
$7.31 | |
Electricity Fees | $13,799 | - |
|
- | |
Natural Gas | $3,872 | 503 |
MMBtu
|
$7.70 | |
Waste Disposal Costs | |||||
Water Usage | $2,011 | 322 |
Tgal
|
$6.25 | |
Water Disposal | $2,128 | 322 |
Tgal
|
$6.61 | |
TOTAL YEARLY COSTS | $80,678 | ||||
RECOMMENDED SAVINGS* | $15,462 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $5,955 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7425: Clean or color roof to reduce solar load | $633 | - |
$504
12,839
kWh
|
$129
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,185 | $2,250 |
$428
10,905
kWh
|
$1,757
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $555 | $676 |
$442
11,251
kWh
|
$113
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,955 | $6,000 |
$3,875
98,736
kWh
|
$1,326
-
kW-mo/yr
|
$431 | $323 | |
05 | 2.7135: Install occupancy sensors | $2,775 | $800 |
$1,147
29,213
kWh
|
$867
-
kW-mo/yr
|
$609 | $152 | |
06 | 2.7241: Install outside air damper / economizer on hvac unit | $3,359 | $4,615 |
$3,359
85,574
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $15,462 | $14,341 |
$9,755
248,518
kWh
|
$4,192
-
kW-mo/yr
|
$1,040 | $475 | ||
TOTAL IMPLEMENTED | $5,955 | $6,000 |
$3,875
98,736
kWh
|
$1,326
-
kW-mo/yr
|
$431 | $323 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs