ITAC Assessment: OR0398
ITAC logo
ITAC Assessment: OR0398
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Lumber
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 2,178,008
ft2
Annual Production 39,910,000
thousand feet
Production Hrs. Annual 4,160
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $281,876 11,412,000
kWh
Electricity Demand $160,506 347,040
kW-mo/yr
Electricity Fees $12,859 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,538,074 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,074

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Ancillary Material Cost Savings Increase in Production Savings
01 4.126: Install sensors to detect defects $1,495,000 $2,000,000 - - - $190,000 $(-150,000.0) $1,455,000
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,011 $85,079 $20,011
810,179
kWh
- - - - -
03 2.3212: Optimize plant power factor $12,184 $12,000 - - $12,184 - - -
04 2.4133: Use most efficient type of electric motors $10,080 $37,263 $5,678
229,880
kWh
$4,402
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $799 $800 $494
20,000
kWh
$305
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $1,538,074 $2,135,142 $26,183
1,060,059
kWh
$4,707
-
kW-mo/yr
$12,184 $190,000 $(-150,000.0) $1,455,000
TOTAL IMPLEMENTED $43,074 $135,142 $26,183
1,060,059
kWh
$4,707
-
kW-mo/yr
$12,184 - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs