ITAC Assessment: OR0396
ITAC logo
ITAC Assessment: OR0396
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Class 8 Trucks
NAICS
n/a
SIC 3713: Truck and Bus Bodies
Sales Range greater than $500
M
# of Employees 455
Plant Area 270,000
ft2
Annual Production 4,260
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $734,027 20,777,000
kWh
Electricity Demand $145,860 54,204
kW-mo/yr
Natural Gas $665,884 51,663
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $387,340 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $345,117

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7226: Use computer programs to optimize hvac performance $164,000 $5,000 - $164,000
-
MMBtu
02 2.7243: Improve air circulation with destratification fans / other methods $167,300 $38,000 $64,300
1,790,000
kWh
$103,000
-
MMBtu
03 2.7224: Reduce space conditioning during non-working hours $42,223 $5,000 $223
6,315
kWh
$42,000
-
MMBtu
04 2.4133: Use most efficient type of electric motors $13,160 $7,740 $13,160
366,268
kWh
-
05 2.7135: Install occupancy sensors $657 $1,995 $657
18,278
kWh
-
TOTAL RECOMMENDED $387,340 $57,735 $78,340
2,180,861
kWh
$309,000
-
MMBtu
TOTAL IMPLEMENTED $345,117 $52,735 $78,117
2,174,546
kWh
$267,000
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs