| Assessment Year | 2001 |
|---|---|
| Principal Product | molded steel |
| NAICS |
n/a
|
| SIC | 3462: Iron and Steel Forgings |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
350,000
ft2
|
| Annual Production | 7,600
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,138,652 | 22,871,400 |
kWh
|
$0.050 |
| Electricity Demand | $9,420 | 207,336 |
kW-mo/yr
|
$0.045 |
| Natural Gas | $2,923,224 | 464,897 |
MMBtu
|
$6.29 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $431,740 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $51,945 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6226: Optimize filtration cleaning / replacement to minimize air resistance | $23,700 | - |
$23,700
534,680
kWh
|
- | - | - | - | - | |
| 02 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $367,000 | $2,750,000 |
$367,000
7,064,000
kWh
|
- | - | - | - | - | |
| 03 | 2.7134: Use photocell controls | $19,090 | $5,610 |
$16,221
312,556
kWh
|
- | - | $187 | - | $2,682 | |
| 04 | 3.5112: Reprocess spent oils on site for re-use | $12,795 | $37,900 | - | - |
$623
-
gal
|
- | $13,972 | $(-1,800.0) | |
| 05 | 2.4133: Use most efficient type of electric motors | $9,155 | $25,870 |
$8,995
180,694
kWh
|
$160
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $431,740 | $2,819,380 |
$415,916
8,091,930
kWh
|
$160
-
kW-mo/yr
|
$623
-
gal
|
$187 | $13,972 | $882 | ||
| TOTAL IMPLEMENTED | $51,945 | $31,480 |
$48,916
1,027,930
kWh
|
$160
-
kW-mo/yr
|
- | $187 | - | $2,682 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs