ITAC Assessment: OR0395
ITAC logo
ITAC Assessment: OR0395
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product molded steel
NAICS
n/a
SIC 3462: Iron and Steel Forgings
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 350,000
ft2
Annual Production 7,600
ton
Production Hrs. Annual 8,760
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,138,652 22,871,400
kWh
Electricity Demand $9,420 207,336
kW-mo/yr
Natural Gas $2,923,224 464,897
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $431,740 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $51,945

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.6226: Optimize filtration cleaning / replacement to minimize air resistance $23,700 - $23,700
534,680
kWh
- - - - -
02 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $367,000 $2,750,000 $367,000
7,064,000
kWh
- - - - -
03 2.7134: Use photocell controls $19,090 $5,610 $16,221
312,556
kWh
- - $187 - $2,682
04 3.5112: Reprocess spent oils on site for re-use $12,795 $37,900 - - $623
-
gal
- $13,972 $(-1,800.0)
05 2.4133: Use most efficient type of electric motors $9,155 $25,870 $8,995
180,694
kWh
$160
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $431,740 $2,819,380 $415,916
8,091,930
kWh
$160
-
kW-mo/yr
$623
-
gal
$187 $13,972 $882
TOTAL IMPLEMENTED $51,945 $31,480 $48,916
1,027,930
kWh
$160
-
kW-mo/yr
- $187 - $2,682
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs