Assessment Year | 2000 |
---|---|
Principal Product | Fruit Puree |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
20,000
ft2
|
Annual Production | 100,000,000
lb
|
Production Hrs. Annual | 6,336
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $234,087 | 6,798,652 |
kWh
|
$0.034 |
Electricity Demand | $61,881 | 219,840 |
kW-mo/yr
|
$0.28 |
Electricity Fees | $21,219 | - |
|
- |
Natural Gas | $1,099,542 | 283,484 |
MMBtu
|
$3.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $118,745 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $110,260 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1231: Establish burner maintenance schedule for boilers | $26,817 | $900 | - | - | - |
$26,817
-
MMBtu
|
- | - | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $15,208 | $26,491 |
$12,024
349,355
kWh
|
$3,184
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,194 | $2,979 |
$1,810
52,462
kWh
|
$244
-
kW-mo/yr
|
- | - | - | - | - | $2,140 | - | |
04 | 2.2621: Modify refrigeration system to operate at a lower pressure | $2,050 | $4,653 |
$2,050
59,496
kWh
|
- | - | - | - | - | - | - | - | |
05 | 2.3212: Optimize plant power factor | $2,241 | $6,400 | - | - | $2,241 | - | - | - | - | - | - | |
06 | 3.1181: Eliminate a by-product | $68,235 | $2,000 | - | - | - | - |
$(-2,345.0)
-
MMBtu
|
$3,180
-
lb
|
$(-12,600.0) | - | $80,000 | |
TOTAL RECOMMENDED | $118,745 | $43,423 |
$15,884
461,313
kWh
|
$3,428
-
kW-mo/yr
|
$2,241 |
$26,817
-
MMBtu
|
$(-2,345.0)
-
MMBtu
|
$3,180
-
lb
|
$(-12,600.0) | $2,140 | $80,000 | ||
TOTAL IMPLEMENTED | $110,260 | $29,391 |
$12,024
349,355
kWh
|
$3,184
-
kW-mo/yr
|
- |
$26,817
-
MMBtu
|
$(-2,345.0)
-
MMBtu
|
$3,180
-
lb
|
$(-12,600.0) | - | $80,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs