| Assessment Year | 1995 |
|---|---|
| Principal Product | Winches |
| NAICS |
n/a
|
| SIC | 3429: Hardware, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 380 |
| Plant Area |
200,000
ft2
|
| Annual Production | 3,744,000
lb
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $299,225 | 6,330,305 |
kWh
|
$0.047 |
| Natural Gas | $14,024 | 2,612 |
MMBtu
|
$5.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $125,277 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $123,719 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,044 | $4,000 |
$3,044
70,633
kWh
|
- | - | |
| 02 | 2.6218: Turn off equipment when not in use | $469 | - |
$469
12,896
kWh
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $1,558 | $5,558 |
$1,558
28,136
kWh
|
- | - | |
| 04 | 3.1191: Change procedures / equipment / operating conditions | $106,051 | $89,900 |
$(-4,439.0)
(-62,720)
kWh
|
- |
$110,490
-
lb
|
|
| 05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $14,155 | $20,000 |
$(-95.0)
(-1,172)
kWh
|
$14,250
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $125,277 | $119,458 |
$537
47,773
kWh
|
$14,250
-
Tgal
|
$110,490
-
lb
|
||
| TOTAL IMPLEMENTED | $123,719 | $113,900 |
$(-1,021.0)
19,637
kWh
|
$14,250
-
Tgal
|
$110,490
-
lb
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs