Assessment Year | 2000 |
---|---|
Principal Product | Canned and pureed fruit |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
170,000
ft2
|
Annual Production | 8,300,000
lb
|
Production Hrs. Annual | 4,223
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,664 | 1,650,938 |
kWh
|
$0.037 |
Electricity Demand | $14,948 | 69,132 |
kW-mo/yr
|
$0.22 |
Natural Gas | $54,311 | 11,142 |
MMBtu
|
$4.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $54,415 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,905 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.7141: Improve cleaning efficiency by maintaining cleaning system | $27,260 | - | - | - | - |
$12,460
-
gal
|
- | $14,800 | - | |
02 | 2.1231: Establish burner maintenance schedule for boilers | $699 | $300 | - | - |
$699
-
MMBtu
|
- | - | - | - | |
03 | 2.2511: Insulate bare equipment | $540 | $345 | - | - |
$540
-
MMBtu
|
- | - | - | - | |
04 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $3,850 | $8,600 |
$(-433.0)
(-14,361)
kWh
|
$(-197.0)
-
kW-mo/yr
|
- | - | - | - |
$4,480
-
Tgal
|
|
05 | 3.4156: Use flow control valves on equipment to optimize water use | $1,096 | $390 | - | - | - | - | - | - |
$1,096
-
Tgal
|
|
06 | 4.441: Install automatic packing equipment | $20,970 | $40,500 | - | - | - | - | $20,970 | - | - | |
TOTAL RECOMMENDED | $54,415 | $50,135 |
$(-433.0)
(-14,361)
kWh
|
$(-197.0)
-
kW-mo/yr
|
$1,239
-
MMBtu
|
$12,460
-
gal
|
$20,970 | $14,800 |
$5,576
-
Tgal
|
||
TOTAL IMPLEMENTED | $32,905 | $9,290 |
$(-433.0)
(-14,361)
kWh
|
$(-197.0)
-
kW-mo/yr
|
$699
-
MMBtu
|
$12,460
-
gal
|
- | $14,800 |
$5,576
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs