Assessment Year | 2000 |
---|---|
Principal Product | Softwood Veneer |
NAICS |
n/a
|
SIC | 2436: Softwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
50,000
ft2
|
Annual Production | 1,280,000,000
thousand feet
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $302,762 | 6,799,238 |
kWh
|
$0.045 |
Natural Gas | $315,161 | 77,419 |
MMBtu
|
$4.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,065,886 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,110 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,383 | $7,000 |
$4,286
125,440
kWh
|
$1,097
-
kW-mo/yr
|
- | - | - | |
02 | 2.4224: Upgrade controls on compressors | $9,673 | $15,010 |
$7,758
227,140
kWh
|
$1,915
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,146 | - |
$900
26,377
kWh
|
$246
-
kW-mo/yr
|
- | - | - | |
04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $3,099 | $885 |
$2,897
84,701
kWh
|
$202
-
kW-mo/yr
|
- | - | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $2,229 | - |
$1,729
50,703
kWh
|
- | - | $42 | $458 | |
06 | 2.8112: Combine utility meters | $1,715 | $4,000 | - |
$494
-
kW-mo/yr
|
$1,221 | - | - | |
07 | 2.4113: Install motor voltage controller on lightly loaded motors | $9,628 | $48,484 |
$7,525
220,397
kWh
|
$2,103
-
kW-mo/yr
|
- | - | - | |
08 | 2.3212: Optimize plant power factor | $7,013 | $19,600 | - | - | $7,013 | - | - | |
09 | 4.131: Modify process to reduce material use/cost | $1,026,000 | $1,337,500 | - | - | - | - | $1,026,000 | |
TOTAL RECOMMENDED | $1,065,886 | $1,432,479 |
$25,095
734,758
kWh
|
$6,057
-
kW-mo/yr
|
$8,234 | $42 | $1,026,458 | ||
TOTAL IMPLEMENTED | $18,110 | $56,369 |
$14,708
430,538
kWh
|
$3,402
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs