ITAC Assessment: OR0376
ITAC logo
ITAC Assessment: OR0376
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Plywood
NAICS
n/a
SIC 2436: Softwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 232
Plant Area 175,000
ft2
Annual Production 110,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $671,995 24,907,972
kWh
Electricity Fees $153,688 -
Fuel Oil #6 $94,938 15,643
MMBtu
Wood $38,250 79,200
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,354 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $17,792 $24,000 n/a - - $17,792 - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,330 $44,000 n/a $6,018
218,933
kWh
$312
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,246 $6,825 n/a $3,508
127,784
kWh
$738
-
kW-mo/yr
- - -
04 2.7134: Use photocell controls $986 $700 n/a $719
26,084
kWh
- - $29 $238
TOTAL RECOMMENDED $29,354 $75,525 $10,245
372,801
kWh
$1,050
-
kW-mo/yr
$17,792 $29 $238
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs