Assessment Year | 2000 |
---|---|
Principal Product | Lighting Fixtures |
NAICS |
n/a
|
SIC | 3648: Lighting Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 600 |
Plant Area |
264,000
ft2
|
Annual Production | 725,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $314,463 | 7,505,569 |
kWh
|
$0.042 |
Electricity Demand | $39,405 | 249,105 |
kW-mo/yr
|
$0.16 |
Electricity Fees | $3,094 | - |
|
- |
Natural Gas | $150,915 | 49,551 |
MMBtu
|
$3.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $174,213 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $78,110 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $29,778 | $20,000 |
$27,723
661,782
kWh
|
$2,055
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,770 | - |
$2,570
61,254
kWh
|
$200
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.3212: Optimize plant power factor | $2,848 | $9,500 | - | - | $2,848 | - | - | - | |
04 | 3.1192: Reduce scrap production | $81,000 | $21,000 | - | - | - | - | - | $81,000 | |
05 | 3.5112: Reprocess spent oils on site for re-use | $45,562 | $2,451 | - | - | - |
$1,512
-
gal
|
- | $44,050 | |
06 | 3.1192: Reduce scrap production | $12,255 | - | - | - | - | - |
$12,255
-
lb
|
- | |
TOTAL RECOMMENDED | $174,213 | $52,951 |
$30,293
723,036
kWh
|
$2,255
-
kW-mo/yr
|
$2,848 |
$1,512
-
gal
|
$12,255
-
lb
|
$125,050 | ||
TOTAL IMPLEMENTED | $78,110 | $22,451 |
$30,293
723,036
kWh
|
$2,255
-
kW-mo/yr
|
- |
$1,512
-
gal
|
- | $44,050 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs